CAPSTONE DEADLINES
Component Due Date
ALL STUDENTS
Logline October 12, 2007
Three Sentences October 22, 2007
Three Paragraphs October 31, 2007
Capstone Proposal November 9, 2007
Script (First Draft) December 13, 2007
Script (Second Draft) January 18, 2008
Script (Third Draft) February 7, 2008
Storyboards February 28, 2008
ALPHA BETA
Production Breakdown March 7, 2008 April 4, 2008
Final Draft of Script March 14, 2008 April 11, 2008
Raw Footage April 8, 2008 May 6, 2008
Rough Cut April 21, 2008 May 19, 2008
Final Cut April 25, 2008 May 22, 2008
Presentations 4/29 - 5/2, 2008 5/28 - 5/30, 2008
*Components lose 10% each day they are late, up to 5
days.
After 5 days, no credit is given, but assignment is still required
prior to moving onto next step.